Work is nearing the end on two additions to the Lyon County Highway Department campus.
Assistant County Engineer Jim Brull had a brief update for Lyon County commissioners during their action session Thursday. Brull says the bridge building could well be finished within a month. The new maintenance shop will likely be done by spring 2024, if not sooner.
The new buildings cost around $5 million in total. Brull says the 21,000 square feet of building space will help the Highway Department have adequate space for its employees and equipment.