For several weeks, KVOE News has been telling you about a major road resurfacing project affecting parts of West Highway 50 in central and west Emporia.
The project to repave West Highway 50 between Prairie and Neosho will have a new component starting this week. City of Emporia Communications Manager Christine Johnson says there will be concrete repair and reconstruction of the northeast corner at Sixth and Rural, one of Emporia’s more prominent ponding spots in cases of heavy rainfall. Johnson says there are potential lane closures affecting northbound traffic on Rural and westbound traffic on West Sixth for up to two weeks, or into early September, once this part of the project begins as soon as Monday.
The full scope of the project will include milling one lane at a time, asphalt overlay across all five lanes of traffic and new pavement markings. The project is expected to last through mid-October, weather permitting, and follows a significant waterline replacement project on West Sixth that affected traffic for several months.